Project Name : Rewinding 4 Units of "MITSUBISHI" 8000 KW Rotor Poles Generators - Batu Sapi Power Station Malaysia
Location of Repair : Workshop PT. MEGA DAYA - Jakarta
Client Name : TOSHIBA International PTY LTD
Client Address : 2 Morton Street, Parramata NSW 2150,
Locked Bag 5209
Paramatta - Australia
Work Performed by Applicant : MITSUI Engineering - Japan
Generator/Motor Data : "MITSUBISHI" 8000 KW Rotor Poles Generators from Batu Sapi Power Station Malasia
Scope of Work :
  • Stripping coil rotor poles
  • Cleaning slot laminated iron rotor poles
  • Preparation tools and equipments for rewinding
  • Rewinding rotor poles
  • Electrical testing after re-winding
  • Completion rotor poles after rewinding
  • Final electrical test rotor poles
  • Packing and delivery rotor poles to site

 

Start and Finished Date : December 15,2004 - March 2005